Tuesday, January 26, 2010







I have been out of town for 4 days and was glad to see that progress continues to be made on the project. The south base anchors have now been drilled and grouted and the crew has moved to the north footing. From the pictures you can see that larger equipment has been delivered to the site.



Today I spent about an hour on site to watch the drilling process. On hole number two they encountered a large rock that caused the drilling process to go very slowly. As the machine ground a hole in the rock, dust waifed across the street.